Maharashtra Shifts 1,600 MW Power Supply to Adani Power

Maharashtra State Electricity Distribution Company transitions to Adani Power for significant electricity procurement.

A
Aapla Nagpur Desk
28 Nov 2026, 9:43 AM IST · 2 min read
Source: Constructionworld
Maharashtra Shifts 1,600 MW Power Supply to Adani Power
KEY TAKEAWAYS
1

MSEDCL will replace 1,600 MW from MAHAGENCO with Adani Power.

2

The new agreement is set at Rs. 5.30 per unit, effective from FY 2030-31.

3

MAHAGENCO may continue operations despite the transition, seeking alternative buyers.

In a significant move, the Maharashtra State Electricity Distribution Company (MSEDCL) has decided to shift its procurement of 1,600 MW of electricity from the aging units of the Maharashtra State Power Generation Company (MAHAGENCO) to Adani Power. This transition was approved by the Maharashtra Electricity Regulatory Commission (MERC) at a tariff rate of Rs. 5.30 per unit, as per the order issued on June 19, 2026. The new arrangement is expected to commence in the financial year 2030-31 under a proposed 25-year Power Supply Agreement.

The transition involves replacing power from several MAHAGENCO units, specifically 420 MW from Units 1 and 2 at Khaparkheda, 340 MW from Units 3 to 6 at Chandrapur, 210 MW from Unit 3 at Bhusawal, and 630 MW from Units 3, 4, and 5 at Nashik. The selected units are notably old, with ages ranging from 38 to 51 years by March 31, 2030, surpassing the 25-year lifespan typically considered in regulatory assessments.

MERC clarified that the termination of existing power purchase agreements does not necessitate the immediate decommissioning of MAHAGENCO's generating units. The state-owned entity can continue to operate these units and sell electricity to other buyers, although MSEDCL will not recover costs associated with these contracts. The projected tariffs for the affected units in the 2029-30 period are estimated to be between Rs. 5.91 and Rs. 7.42 per unit, with an average of Rs. 6.77 per unit.

Adani Power's successful bid followed a competitive process, which included a voluntary discount of 13.75% on the energy charge, bringing the initial discovered tariff down from Rs. 5.49. The company received the Letter of Award from MSEDCL on March 15, 2026, and will supply power from an upcoming ultra-supercritical thermal project. This transition raises concerns for MAHAGENCO as it will need to find alternative buyers for the affected capacity, impacting operations and workforce arrangements at Khaparkheda and Chandrapur.

Looking ahead, the implications of this shift will depend on the commissioning of the new capacity and the decisions made by both MSEDCL and MAHAGENCO regarding workforce management. The MERC order does not outline any plans for employee retrenchment or redeployment, leaving the future of the workforce uncertain as the energy landscape in Maharashtra evolves.