Adani Green Energy Confirms ₹5,675 Crore Cost for Satara Project

Adani Green Energy Ltd affirms the total cost of its 1,500 MW hydroelectric project in Maharashtra amidst environmental scrutiny.

A
Aapla Nagpur Desk
18 Nov 2026, 10:33 AM IST · 2 min read
Source: TOI
Adani Green Energy Confirms ₹5,675 Crore Cost for Satara Project
KEY TAKEAWAYS
1

The total estimated cost of the Tarali project is confirmed at ₹5,675 crore.

2

Environmental clearance was granted by the Union Ministry in February 2022.

3

The Maharashtra forest department issued a stop-work notice due to lack of National Board for Wildlife approval.

Adani Green Energy Ltd (AGEL) has officially confirmed that the estimated cost for its proposed 1,500 MW pumped storage hydroelectric project in Tarali, located in the Patan taluka of Satara district, stands at ₹5,675 crore. This declaration comes amid ongoing controversies regarding the project's environmental impact, particularly concerning its proximity to ecologically sensitive areas.

The project has faced scrutiny after AGEL projected a lower environmental cost for the region surrounding the Sahyadri Tiger Reserve and Koyna Wildlife Sanctuary. The Maharashtra government is reportedly considering withdrawing a demand from the forest department, which sought 4% of the total project cost for wildlife conservation efforts in the area. This demand was communicated to AGEL through a letter from the Principal Chief Conservator of Forests (Wildlife).

AGEL clarified that the previously mentioned ₹56.75 crore was not the total project cost but rather related to preliminary activities, including surveys and geological studies necessary for feasibility assessments. The company indicated that it had already deposited 1% of the applicable cost with the government as part of the requirements for the survey and investigation phase, which received clearance from the State Board for Wildlife in March.

During a recent meeting with AGEL officials, discussions centered on project requirements, environmental conservation measures, and the recommendations from the forest department, emphasizing the need to balance infrastructure development with ecosystem protection. The absence of a specific eco-sensitive zone (ESZ) notification means that a 10km radius guideline applies to the project, as per Supreme Court directives.

In a written statement to wildlife authorities, AGEL noted that it had received environmental clearance from the Union Ministry of Environment, Forest and Climate Change in February of last year and consent to establish from the Maharashtra Pollution Control Board in April. The company stressed that no forest land is involved in the project, and it has already obtained a non-forest land NOC. However, a stop-work notice was issued by the state forest department on November 13, halting all activities due to the lack of National Board for Wildlife approval. This situation follows concerns raised by Satara's Honorary Wildlife Warden regarding discrepancies in the project's declared costs, prompting calls for an independent inquiry into potential misrepresentation.