Maharashtra Forest Department Considers Lifting Work Halt on Adani's Hydropower Project
The Maharashtra Forest Department may soon lift the stop-work order on Adani Green Energy's Tarali project following clarifications on project costs.
The halt on construction was initiated on November 13 due to clearance concerns.
Adani clarified that the project's total cost is Rs. 56.75 billion, addressing previous misunderstandings.
The forest department is currently reviewing the company's submissions before making a final decision.
The Maharashtra Forest Department is contemplating lifting the stop-work order on Adani Green Energy's 1,500 MW Tarali pumped storage hydropower project in Satara district. This consideration follows a meeting where company representatives provided clarifications regarding the project's financial details to Forest Minister Ganesh Naik. The halt in construction, which began on November 13, was prompted by concerns related to an online clearance filing.
During the meeting, Adani's representatives reassured officials that the estimated cost of the project remains at Rs. 56.75 billion. They clarified that a separate figure of Rs. 567.5 million was solely for site investigations, geological studies, and project planning, not indicative of a reduced overall project cost. This clarification was crucial in addressing allegations that the company had drastically lowered its declared cost to minimize its mandatory wildlife conservation deposit for the Sahyadri Tiger Reserve.
The wildlife conservation deposit, based on the full project cost, would amount to Rs. 2.27 billion, contrasting sharply with the Rs. 22.7 million calculated from the lower figure. The meeting included key officials such as Sanjay Khandare, the additional chief secretary for forests, and senior wildlife officials, who are now reviewing the documentation submitted by Adani Green Energy.
The forest department's decision to halt construction was influenced by reports suggesting that work had commenced without the necessary approvals from the National Board for Wildlife. Adani Green Energy has asserted that the construction sites do not encroach on protected forest land and that their wildlife clearance proposal is under review. The department's scrutiny of the company's submissions will determine whether the stop-work order will be revoked.
As the situation develops, the forest department is expected to make a decision soon. The outcome will have significant implications for the project timeline and for Adani Green Energy's operations in Maharashtra, as they await the department's final verdict on the matter.