Ward 5 Secures ₹1.40 Crore for Slum Development Projects
Nagpur's Ward 5, led by Laxmi Hattithele, tops the list with 18 approved slum works, raising concerns over fund allocations.
Ward 5 received the highest allocation of ₹1.40 crore for slum projects.
A total of 162 projects worth ₹12.71 crore were approved across 26 wards.
An additional ₹15 crore may be needed to meet the proposed development costs.
In a recent review of slum development funding, Nagpur's Ward 5 emerged as the leader, securing ₹1.40 crore for 18 approved projects. This information comes amid ongoing scrutiny regarding the allocation of funds by the Nagpur Municipal Corporation (NMC) under its Durbal Ghatak (Weaker Sections) Committee. The data covers the period from April 1 to October 1, revealing that Ward 5, represented by committee chairperson Laxmi Hattithele, received the most administrative approvals compared to other wards.
Following Ward 5, Ward 1 received ₹1.29 crore for 16 projects, while Ward 13 was allocated ₹1.16 crore for 12 works. Other wards, such as Ward 11 and Ward 4, received ₹84.45 lakh and ₹79.49 lakh, respectively. In contrast, Ward 15 received the least funding, with only ₹4.94 lakh approved for a single project. The total number of approved projects across all wards stands at 162, amounting to ₹12.71 crore, although 12 wards did not receive any approvals.
The allocation of funds has raised questions, particularly since development proposals totaling nearly ₹55 crore were submitted against a budget of approximately ₹35 crore. On November 17, Hattithele formally requested the municipal commissioner, Vipin Itankar, to cancel all allocation letters and initiate a thorough review of the proposals. Official records indicate that Hattithele has recommended 521 works worth ₹39.31 crore since April, with only nine projects valued at ₹60 lakh having received work orders so far.
Civic officials estimate that an additional ₹7 crore will be necessary to complete the proposed works, which include cement flooring, sewer lines, and paving block installations. With only ₹25 crore currently allocated under the committee's budget, officials suggest that an extra ₹15 crore may be required from other budget sources to fulfill the proposed projects and ensure proper allocation.
Hattithele expressed her frustration over the lack of response from the administration regarding her request and announced plans to convene a committee meeting to determine the next steps. The situation remains fluid as stakeholders await further developments regarding the allocation of funds and the implementation of slum improvement projects.