Construction Progresses on Rs619-Crore Wardha Road Flyover

The ongoing construction of the Chinchbhuvan–MIHAN flyover is marred by traffic chaos due to rampant wrong-side driving.

A
Aapla Nagpur Desk
17 Nov 2026, 2:04 AM IST · 2 min read
Source: TOI
Construction Progresses on Rs619-Crore Wardha Road Flyover
KEY TAKEAWAYS
1

The Chinchbhuvan–MIHAN flyover spans 2.69 km and costs Rs619 crore.

2

Traffic congestion has increased due to wrong-side driving and construction activities.

3

The project is expected to be completed by November 2027.

In Nagpur, the construction of the Chinchbhuvan–MIHAN Interchange flyover, valued at Rs619 crore, is making significant strides. However, the project is facing severe challenges, particularly from rampant wrong-side driving and heavy traffic congestion on Wardha Road. As of now, most of the piers for the 2.69-km-long flyover have been erected, with the National Highways division of the Public Works Department (PWD) beginning to launch segments from the MIHAN Interchange end.

A recent visit to the site revealed that many motorists, especially those accessing nearby commercial establishments and schools, are frequently driving on the wrong side of the road to avoid longer U-turns. The construction barricades have narrowed the carriageway, exacerbating the traffic situation and heightening the risk of accidents. Previously, the PWD had removed dividers and merged the service road with the main carriageway to facilitate traffic flow during construction, but this has led to confusion, with many drivers treating the area as a service road and driving against the traffic flow.

Ajni Traffic Zone police inspector Suresh Vasekar acknowledged the ongoing issues, stating that the construction has created multiple bottlenecks. He noted that locals continue to drive on the wrong side, as they still perceive the road as a service route despite its integration with the highway. Vasekar also pointed out that roadside parking, commercial activities, and the necessity for longer U-turns are further complicating the situation. The traffic police, in collaboration with the PWD, are actively monitoring the area and implementing various measures to alleviate these problems.

Commuters have reported significant delays, with travel times from Nagpur to Butibori increasing from approximately 20 minutes to nearly 45 minutes due to the construction of the flyover and ongoing Metro work further along Wardha Road. The six-lane flyover is being constructed along one of Nagpur’s busiest corridors, linking the city with major destinations such as Wardha, Hyderabad, Yavatmal, and Mumbai. Despite the rapid progress of the project, traffic remains heavily congested, particularly between Chinchbhuvan and the MIHAN Interchange.

The Chinchbhuvan–MIHAN flyover project is set to be completed by November 2027, with a total cost of Rs619 crore. The flyover will span 2.69 km and feature six lanes, aimed at improving connectivity and easing traffic congestion in the region.